UWG Word Art

Personally Serving You-
Faster. Friendlier. Easier.

How was our service?

Campus Planning & Facilities

Featured Project

J-40 – Health and Wellness Building  

Project Description: The HW Building will house the academic department of Physical Education and a 7200 seats arena with facilities for the Athletic Department. The main purpose of this facility will be for instructional use, however it will also support other activities such as freshman convocation, graduation, athletic events, trade shows/conventions, concerts and camps. 

The proposed facility is approximately 123,000 square feet and will seat up to approximately 7200 for end stage events. Since this facility will host a wide variety of activities, the lobby/prefunction area will serve as a central access point to allow access into the various activities during different parts of the day. Sound attenuation between the instructional spaces and activity space is very important. 

Current Update: As of June 2nd, 2007, the University has submitted and received approval from the Vice Chancellor for Facilities for a new SCL of $ 23,066,105.  This number reflects all cost management options investigated and approved by the University, reduction of the owner’s contingency to increase the SCL and the approval of floor plan layout scheme K.  The team will now concentrate in working the schedule for a building completion of January 2009 and completion of documents to obtain final pricing and  signing of the Guaranteed Maximum Pricing contract  by fall 2006.  Construction will ideally start late summer 2007.

 

Design and Management Method: The design phase of the project follows a model using a Project Advocate to be the liason between the different users and the design team. 

The construction of the project will follow a model using a Program Manager to manage all aspects of the project and a CM at risk with a Guaranteed Maximum Price, rather than hard bid, to build the project 

The design and management of the project will follow the model first implemented with the Geosciences project. A Project Advocate has been selected to provide first line of contact between all the departments involved and the design team. This advocate is a member of the academic community, rather than a technical person. All issues needing resolution are worked out internally by the Project Advocate and the departments involved, then the resolution is transmitted to the architect. Additionally, a Core Executive committee composed by Vice Presidents and Deans provides executive oversight for the project. Executive briefings are scheduled at the end of every site visit and workshop conducted by the architects. 

The intent of this model is to allow complete involvement and participation at all levels of the University, to allow ownership of the project by the users, and to provide clear lines of communication between the users and the design team. 

The construction of the project will be implemented following a model that includes a Program Manager and a CM at risk. The Board of Regents will be the owner, the University will be the user and the GSFIC will have minimum involvement in the process.

Project History: A series of work sessions took place to verify the organization, operation, and function of the proposed spaces of the HWLLC. Interviews were conducted with representatives from involved departments. The Programming Cards were a result of these interviews. Spaces and square footages were confirmed and adjusted according to the needs of the various groups. The Space Program was developed as a result of these work sessions and the Programming Cards. Some areas were additionally adjusted to allow the project to fit into the allocated budget. 

Total Project Cost is $27,784,000.00.(Revised to $29,451,040) The Construction Cost (Stated Cost Limitation) is $21,451,000.00.(Revised to 22,790,000) The A/E (fixed) Fee is $1,290,000.00. 

In May 2003, the Office of Facilities, Board of Regents, provided Rosser International, Inc. with a professional services contract for $99,090.00 to begin the development of design documents. Rosser expects to begin initial design work in September, 2003. 

UWG has requested an allottment registry from Adamson Hall, Project I-62B in the amount of $388,871.96 to augment Rosser International's contract. 

Amount approved and added to Rosser's Contract. 

On January 14 and 15, a design kick off meeting and Program Validation work sessions took place. All departments and entities involved in the project mett with the architects to review and confirm their needs. 

As a result of these meetings, the Nursing department and HPE modified their program. Nursing functions will also accomodate the Center for Caring and an outpatient clinic. HPE eliminated the racquet ball courts and included two additional labs. All of these revisions to the program were accomplished within the approved square feet. 

As of February 9,2004, a design session to discuss adjacencies and massing took place February 3 and 4. The architects reviewed the modified program and validated the modifications against the budget. The sessions involved extensive discussions with HPE and Athletics concerning the layouts of the courts to allow teaching and game practices simultaneously. At the end of the sessions, both departments were satisfied with the architects preliminary design. 

Several general issues need to be studied for resolution. 

1                      The location of the building will impact the design and location of the adjacent north/south road proposed in the master plan, because of constraints imposed by possible wet land issues in the east side.

2                      Noise level at the courts need to be considered when selecting separation means between courts. 

3                      The University needs to provide guidance concerning CATV availibility for every space in the Building. 

4                      Because of questions concerning availability of sponsors, the building will include a basic kind of scoreboard. The University needs to develop a marketing/solicitation plan to fund a more sophisticated score board. 

 

Design work shops are scheduled for February 24,26,27. 

The architectural team expects to develop, on site, the floor plans and basic elevations, working with the University users, in a charrette style work shop. 

Design Workshops are scheduled for February 25, 26, 27. 

Agendas have been prepared and distributed. At the end of the sessions, it is the Architect's intent to have three possible layouts for the building for all parties to select the preferred scheme and building massing. 

The workshops of February 25,26,27 resulted on three schemes mainly for massing and site location. A preferred scheme was identified by the University and the architectural team will develop this scheme and come back for a presentation to the users and the core committee. It is anticipated that this sessions will take place in early April. 

A meeting has been scheduled for April 15 in the afternoon. The architects will present the preferred solution including hard line floor plans and massing for the building. As of this date, it appears that the funding for the building will not be approved this legislative session. The project will stay in the list of projects to be funded for the 2005 session. 

A meeting was held on campus on June 9th,2004. The architects presented revised schematic plans, massing and elevations for the building. Detailed comments were requested from the users for both the final draft of the program and the revised schematics. The users are working with the Project Advocate to finalize their comments and transmit them to the architects. 

It is anticipated that a working meeting will be scheduled on campus early July. 

A meeting was held July 12 at UWG, with the BOR Office of Facilities, the campus administration and the architects. The architects presented the design and some discussions were held concerning constructibility issues for HVAC equipment (if located on roof) and avoidance of retaining walls. 

A meeting was held on campus on June 29th,2004 with the Nursing department to finalize the floor plan layout for the department. Agreement was reached for the optimal layout that will serve nursing and that will work with the building design. 

Similar meetings will be scheduled with the PE and the Athletic Departments. 

Meetings were held with the Physical Education and Athletic Departments to review plan layouts for their respective spaces. The layout was acceptable to PE and for Athletics, except for the training room, it was also

acceptable. The training room issues will be resolved with the design team. 

The Board of Regents office has scheduled a meeting with the Office of Planning and Budget to review status
of project with the objective of placing this project in line for definitive funding next fiscal year. This meeting will
take place August 17, 2004. 

The program documents for the building have been approved and were submitted by the University to the
Board of Regents, August 5, 2004 for final approval. Square Footage for the building has been reduced to
162,000 SF (revised to 168,654). The total project cost has been revised to $29,451,040 with an Stated Cost
Limitation of $22,790,000. These figures reflect a 6% escalation cost approved by the Board of Regents. 

Schematic Design documents are in the process of being reviewed in preparation for submittal to the Board of
Regents late August, early September. 

A presentation to the Office of Planning and Budget took place August 17,2004. The project was presented as
an information item in preparation for the request for project funding in the upcoming legislative session of
January 2005. 

Schematic Design documents are in the process of being reviewed in preparation for submittal to the Board of
Regents late August, early September. The University is working with the architects to identify and select
possible deductive alternates as required by the guidelines of the Board of Regents. 

As of September 13, Schematic Design documents are in the process of being reviewed in preparation for
submittal to the Board of Regents. The University and the architects have identified possible deductive
alternates as required by the guidelines of the Board of Regents. These alternates will be reviewed by the users
and the administration and prioritie will be developed for incorporation in the final documents.

Preliminary Drawings and Specifications are also in process of review by the University. The preliminary
approval will be submitted to the Board of Regents after the review process is completed. 

As of October 11, the Schematic Design documents have been approved and submitted to the Board of
Regents. 

Preliminary Design documents have been received and reviewed by the institution with the exception of the
preliminary furniture proposal. A meeting has been scheduled for October 20, to start the discussion on
furniture. It is anticipated that the PD drawings will be submitted to the Board of Regents by the end of October.
According to the procedures of the Board of Regents,a meeting must be scheduled with architects, institution
and office of facilities for the Regents to review this submittal. It is anticipated that this meeting will take place
early November. 

As of November 1st, 2004, Preliminary Design Submittal has been received. The booklets will be signed by all
User departments and the University Administration before a formal submittal to the Board of Regents is made.
Anticipated date of submittal, November 5th.
As of November 8, the preliminary design submittal is undergoing the signature and approval process. 

The architect has scheduled meetings for November 9 with sound consultants and AVand IT consultants to
review sounds requirements for Arena, AV requirements for classrooms and to answer questions and concerns
from ITS regarding data and telephones.
As of January 5,2005, 100 % Construction Drawings have been received by the University. Drawings will be
reviewed and comments submitted to the Architects for final completion of bidding documents. 

A meeting has been scheduled with all users and Core Committee on January 13, 2005. The architects will
present budget challenges regarding AV and FF&E items for decision by the University.
As of February 1st, 100% review comments have been submitted to the architects. Architects are preparing
responses to the comments. A meeting will be scheduled to discuss the comments and architects response. 

On January 26 a meeting was held to review IT plans. All questions appear to be answered. At the meeting the
IT department indicated that the drawings were to their satisfaction. Engineers will finalize for incorporation in
the final set of drawings. At this meeting, infrastructure for AV was discussed,reviewed and agreed upon by the
IT department.
Partial comments to the 50% and 100% submittals were received by the University on February 3, 2004. A
meeting will be scheduled with the architects and engineers to review and finalize comments.

The University is preparing a list of possible acquisitions of FF&E items that could be purchased by end of fiscal
year 2005. This direction was provided by the administration to try to facilitate resolution of budget problems
impacting FF&E and AV.
Additional information concerning AV and IT has been received and is been reviewed by the University. 

The University continues to work on purchasing strategies to supplement equipment and furnishings budget. 

The approved deductive alternates list is in process of been revised. The reduction of lenght for the pool has
been eliminated from the list and single ply roof materials and elimination of cable trays are been considered as
additional alternates.
As of March 21,2005 the University has requested that a different roof material(less costly) be used and that the
savings realized through this change be applied to include proper lighting to support the AV capabilities for the
classrooms, which are not presently included. 

The architect has advised that a new 100% set of drawings will be issued for review the week of March 28.
As of April 1, 2005 drawings have been received from the architects and will be distributed to the users, ITS
and Auxiliary Services for review. 

A meeting will be scheduled with the architects to resolve pending issues such as the lighting of classrooms for
AV, the roof replacement and the finalization of the deductive alternates list.
As of April 14, funding for the project has been delayed by the Legislature. Only Design funds were approved. 

A meeting has been scheduled with the architects to discuss implications of this delayed funding. Also, status of
the project and alternates will be reviewed.
As of May 5, 2005, the university continues to review drawings to insure that all requirements have been
incorporated into the project. Several meetings have been held with the architect and engineering team. 

The deductive alternates list has been revised following the direction provided by Dr Hynes and Mr Bill Gauthier
and the revisions have been approved by them. 

The Av and Data drawings are been revised, following a meeting held at the University, May 2. The engineers
will incorporate all of the requirements and submitt completed drawings for AV and Data for a final review, May

14. Once these drawings are throughly reviewed by the University for compliance and providing that they do not need further revisions, final contract document sets will be forwarded by the Architectural team to the University for final approval and forwarding to the Board of Regents. As of May 26, 2005 completed drawings for Data, Telephone and AV have been submitted to the University for final review. Comments are due to architect the first week of June. The architectural team is proceeding with submission of the drawings for Fire Marshal and Peer review. Once the reviews are completed, the approved submittals will be sent to the Board of Regents. 

The completed drawings will be approved and signed by the users committee and the University administration.

As of June 9, UWG and Rosser are working on the preparation of the final submittal of the documents to the
Board of Regents. Uwg must provide Rosser with the final comments on AV and Data, and then final
documents will be released for signature by UWG administration.
As of July 5, Rosser has received latest comments from UWG. Drawings will be updated and submitted to the
Fire Marshal. Once their comments are received, project will be ready for final review and approval by the
institution. Anticipate that FM comments will be received by architects in about six weeks. 

As of July 27 no change on status.
Per Rosser, as of August 8, 2005, Drawings have been reviewed through the mandatory peer review process.
Comments from this review are already incorporated into the drawings. The drawings are at this time under
review by the State Fire Marshal' office, Carrolton Health Department and GSFIC. Once all of these reviews are
completed, drawing package will be ready for final submission by the University to the Board Of Regents. It si
anticipated that all these reviews will be completed by late September.
As of September 9, 2005, the Architect advises that constructibility peer review as directed by the Board of
Regents is completed. Comments have been received from the Fire Marshal/GSFIC and they will be
incorporated in the drawings. City of Carrollton Health Department has reviewed and approved the swimming
pool.

Architect to advise the University as to a date that final sets of drawings will be submitted to the University for
Final approval and submission to the BOR.
As of September 22, UWG has received from the architects copies of comments from GSFIC and Peer review.
Architect must notify UWG when drawings will be completed revised and prepared for final submittal to BOR.
As of December 12,2005, Architect advises that revised drawings will be send out to the University on
December 16. Review meetings will be scheduled with University personnel and consultants for the following:

1                      Data and AV

2                      Security/Hardware/Fire Alarm 

3                      Hardware

4                      Lighting controls 

 

These meetings will be the final attempt by the project team to insure that everything is covered by the documents to avoid costly Change Orders during construction. 

As of March 20, 2006 it appears that the project will be funded on the 2006 supplemental budget. The University, the Board of Regents and the architects will have to investigate options concerning the building as presently designed since it appears that the funds approved will not be sufficient to cover the present design.

As of April 10, 2006, the project is included in the supplemental 2006 budget. This budget is awaiting the governor's signature. 

Design for this project will have to be modified to meet the approved budget. 

As of August 24, 2006, RFQ for Program Management Services have been received and short listing is proceeding. Interviews for the short listed firms have been scheduled for September 6. Selection will be based on qualifications and the best fit for the project rather than fee.

As of September 12, 2006, interviews were held at the Office of Facilities for the Board of Regents with four short listed firms. The committee has submitted a recommendation for the most qualified firm, determined thru the interview, to be engaged. This recommendation must be internally processed and approved by the Office of Facilities. Once approval is obtained and firm is notified, the BOR will negotiate fees.

As of November 2006, Carter has been chosen as the program Manager and Skanska has been chosen as the Construction Manager for  the project. The office of Facilities is negotiating fees and contracts with both firms.

As of November 2006, Carter has made a preliminary presentation to the University outlining opportunities for bringing the project  within budget.  Due to the delayed funding and rising construction costs, it appears that the budget can not support 169, 000 square feet . Per Carter in order to met the budget, the building square footage must be reduced to 120,000 SF.

As of January 2007, Carter presented alternative ways to bring the project within budget. UWG has agreed to remove Nursing, Continuing Education and the pool from the building in order to achieve an square footage figure of 120,000 as recommended by the Program Manager. The architects will now prepare a Schematic package for pricing by the CM. Pricing should be available by March 1st, 2007. A meeting will be scheduled with the Office of Facilities to review the programmatic changes of the building and the reconciliation with the Stated Cost Limitation.

As of March  2nd, 2007, BOR has approved programmatic changes and a preliminary cost model has been received from Skanska.  The estimate appears to be 7 m8illions over the SCL.  The project team will work towards studying cost management alternatives and solutions to bring the project within budget.

As of  April 30, 2007 the project team has incorporated all cost management alternatives in the project and is ready to present preliminary recommendations from the University to the project manager at the Office of Facilities. The University has agreed on the design layout and in requesting the use of contingency funds to raise the SCL to a slightly higher number.

 

 

Funding Source: Major Capital Budget: $30,449,867

Project Manager: Elsa Pena Architect/Consultant: Rosser International, Inc. Contractor: Skanska. Program Manager:  Carter.  Project Approval Date: June 9, 1999 Estimated Completion Date:  January 2009

Renderings/Photos

                   Project Schedule

                   Proposed Building Entrance

                   Health Wellness Lifelong Learning Center website/message board

 

Last Updated:

 

Campus Planning & Facilities | News | About Us | Contact/Support |

Last Modified: 7/18/2007